How to assign duration to an activity?
Martin Tsekov avatar
Written by Martin Tsekov
Updated over a week ago

To assign a duration value to an activity:

  1. Select an activity, located in your project of scope.

  2. Select the Duration column.

  3. Enter the duration value in the number of days.